Summary of Approved Projects (Food Processing) as on June 2013

Minutes of the Meeting: Financial Bid Opening and Evaluation & Ranking of Financial Proposals for the “Selection of Technical Consultant”
July 3, 2013
Monthly Progress Report for Food Processing Sector projects approved under “Scheme for Integrated Development of Food Processing Sector” and “Scheme for Food Parks” for the month of June 2013 (PAMC approved)
July 3, 2013

Summary of Approved Projects (Food Processing) as on June 2013

Projects Numbers Units in Commercial Production Grant Released Approved Project Cost Grant Sanctioned Total Grant Release Approximate Employment Generation in Numbers
Number of Projects (INR in Lacs)
RICE MILLS 64 35 36 55939.01 13211.17 4475.59 2201
WHEAT MILLING 19 10 12 16137.98 4357.47 1640.55 585
MAIZE PROCESSING 16 9 9 18809.44 2334.05 632.00 31
RABC 33 12 25 27587.39 8104.90 3307.93 1090
F&V PROCESSING 9 6 6 5282.04 1516.46 999.94 326
MILK PROCESSING 7 4 2 11128.67 2606.42 466.75 439
MAKHANA PROCESSING 2 1 1 134.73 39.06 4.17 42
HONEY PROCESSING 2 2 2 224.14 61.78 51.80 32
BISCUIT MANUFACTURING 4 4 4 16615.07 2000.00 2000.00 1581
EDIBLE OIL MANUFACTURING 7 5 7 45151.70 2675.06 1816.93 1898
OTHER PROJECTS 11 7 6 15064.46 3053.24 841.12 203
FOOD PARK 1 0 0 15396.00 1500.00 0.00 3000
TOTAL 175 95 110 227470.63 41459.61 16236.78 11428